Case Study: Lillian Vernon achieves 15% more facility capacity with PeakLogix mezzanine storage expansion

A PeakLogix Case Study

Preview of the Lillian Vernon Case Study

Lillian Vernon - Customer Case Study

Lillian Vernon needed to maximize the square footage in its existing distribution center before the holiday shopping season, and it had to be done without disrupting ongoing operations. PeakLogix provided an additional warehouse storage solution centered on adding a new mezzanine to expand capacity within the facility.

PeakLogix coordinated the building of 85 column footers, installation of a 24,000-square-foot mezzanine, and pouring of a concrete deck while the warehouse remained operational. The project increased facility capacity by 15%, improved picking efficiency by making more product lines accessible, and created room for additional embroidering machines as sales grew.