Louis Berger‑Egis Rail JV, working on the Doha Metro project in Qatar, faced significant document control challenges: multiple versions to manage, slow manual communications across organizations, inefficient reporting, and the need for a complete, accessible project record.
By implementing Aconex to automate document control, remove hard-copy reviews, enable ad hoc reporting, and archive files in a single neutral database, the team cut document controllers from 15 to 6, saved an estimated US$314,600 in labor and US$26,400 in printing/handling, and reduced report preparation from a full week to minutes.
Mohammed Zahid Khan
Document Control Manager/Project Controls Engineer