China Major Bridge Engineering Co used Aconex on the GuangFo Expressway Foshan Section S4 Project in Foshan, China. The joint-venture project struggled with cross-organization communication, subcontractor collaboration, lengthy review and approval cycles, and inconsistent information management, so they needed a neutral, standardized platform to streamline coordination.
By adopting Aconex templates, configurable workflows and flexible naming conventions, the project was operational in three weeks (75% faster than before) and saw 40% faster RFI/submittal/drawing reviews, 75% faster document handover (20 days vs. three months), 60% faster monthly reporting (one week to two days), and a 66% reduction in required document controllers. The neutral platform improved collaboration and overall project efficiency.