Oracle Aconex supported the construction of Venda Nova III, a US$438.6 million, 736 MW pumped‑storage hydroelectric station in Portugal featuring nearly nine kilometers of underground tunnels and a 50‑plus‑metre below‑ground powerhouse. The multinational consortium required a centralised, secure and easy‑to‑use system to manage project files and enable fast, effective communications among dispersed teams.
Aconex provided a single web‑based collaboration platform with construction‑specific document control, workflow management and real‑time access, distribution and tracking. The solution delivered consistent project workflows, strong security and usability, and improved project‑wide efficiency, transparency and accountability.