LNG Canada, a major liquefied natural gas export facility project, engaged nPlan to mitigate delivery risk and avoid costly schedule overruns during its large-scale construction. The challenge was to gain an objective view of schedule risk, supplement their traditional analysis, and identify potential issues before they impacted the critical path and budget.
nPlan implemented its AI-led forecasting and risk management service, performing over 30 analyses of the project schedule. This enabled LNG Canada to identify and mitigate risks proactively, discovering 150 days of avoidable delay. Key successes included optimizing the facility's commissioning sequence, which may avoid two months of delay. nPlan's integration into the project's workflows provided data-driven insights that directly contributed to keeping the project on time and on budget.