Case Study: Media Information Company achieves 45% energy cost savings with Nlyte Energy Optimizer

A Nlyte Software Case Study

Preview of the Media Information Company Case Study

Nlyte Energy Optimizer’s real-time monitoring helps a Media/Information company safely consolidate to blade servers, saving 45% in energy costs

a media information company faced challenges with high energy costs and limited space in its three data centers. To avoid building a new facility, they planned to consolidate traditional servers into more efficient blade servers but needed a way to do this safely without risking circuit overloads and downtime. They turned to Nlyte Software and implemented the Nlyte Energy Optimizer solution for real-time circuit monitoring.

Nlyte Energy Optimizer provided real-time monitoring of circuits, alerting the team to potential overloads and enabling confident server consolidation. The solution allowed the media information company to consolidate 1,243 traditional servers onto just 137 blade servers. This resulted in massive savings of $586,570 in power costs and a reduction of 2,841 tons of CO2 emissions. The investment in the Nlyte software paid for itself in just 2.6 months.


Open case study document...