Porocel, a global leader in catalyst services and producer of activated alumina with multiple manufacturing sites, faced a growing maintenance problem at its Little Rock plant: a 16-person team operating largely reactively with processes that hadn’t scaled with the business. New maintenance planner Mike Goldman audited the operation, discovered an unused MPulse installation on the server, and set out to get the plant up and running on a structured CMMS within 60 days.
Porocel upgraded to MPulse 8 in the cloud, built simplified custom work-order and record views for technicians, and ran targeted training. Within two months they moved to electronic, instantly assigned work orders (saving roughly 30–60 minutes per tech per day), began automatically generated preventive maintenance, strengthened ISO 9000 readiness, and started inventory tracking—delivering measurable efficiency and process control in 60 days.
Mike Goldman
Porocel Maintenance Planner