mJobTime
16 Case Studies
A mJobTime Case Study
Hellas Construction, an Austin-based contractor specializing in sports facilities, faced significant cost control challenges due to a manual time reporting system riddled with errors. The process was so intensive it required two administrators to work 60 hours a week on payroll. They turned to mJobTime's field reporting software for a solution.
mJobTime implemented a flexible platform featuring barcode scanning and custom equipment groups that integrated with the contractor's accounting software. The solution reduced Hellas Construction's administrative time by over 30 hours per week, resulting in monthly savings of $10,000 and achieving nearly 100% accuracy in per diem reporting.