MaxMine
9 Case Studies
A MaxMine Case Study
A large open pit coal mine was experiencing frequent and costly damage to its truck frames, which led to significant downtime and unreliable payload measurements. They engaged MaxMine to address the challenge using its maintenance-focused solution.
MaxMine identified that incorrectly overcharged suspension cylinders were the root cause. The vendor helped recharge the suspensions. This implementation by MaxMine resulted in a 12% increase in machine availability and a 91% reduction in daily suspension-related alerts.
Large Open Pit Coal Mine