Case Study: a US energy utility with multiple compressor stations achieves reliable compressor station controls upgrade with LSI

A LSI - Logical Systems Inc Case Study

a US energy utility with multiple compressor stations cuts control system failures to zero with LSI in 2 weeks

The customer, a large US energy utility, faced a critical challenge when supply chain issues delayed a planned upgrade to the aging control systems at its remote compressor stations. With winter approaching and the schedule becoming urgent, the utility turned to vendor LSI - Logical Systems Inc for a solution to ensure reliable natural gas delivery.

LSI developed an alternative solution using in-stock Emerson Rx3i hardware and a new version of GE CIMPLICITY HMI. The upgrade was completed within the client's two-week shutdown window. The results were significant, with control system failures dropping to zero, eliminating expensive downtime and service calls. The successful project solidified LSI's role as the utility's trusted systems integration provider for ongoing work.


View this case study…