Saint Gobain, a contractor on a large commercial project in Bordeaux, France, faced the challenge of laying out approximately 13,000 ceiling hanger points for a floating ceiling installation. The traditional manual method for this task was time-consuming and prone to inconsistency, creating a significant bottleneck for the project's schedule.
LightYX implemented its laser projection solution to bring the digital layout directly onto the jobsite surface. This allowed the crew to mark hanger point locations with speed and accuracy. Using LightYX's technology, the estimated layout time was reduced from 59 days to just 9 days, saving 50 working days and achieving an 85% reduction in time compared to the manual method.