A Kinaxis Case Study
Celestica, a global electronics manufacturer with operations in Asia, the Americas and Europe, faced complex multi‑site supply chains and rapidly changing customer demand. The company needed to standardize available‑to‑promise (ATP) and clear‑to‑build (CTB) capabilities, improve analytics and reduce planning latency so different sites could coordinate and provide clear, timely answers to customer requests.
By deploying Kinaxis RapidResponse, Celestica gained fast, scalable ATP/CTB and robust what‑if analysis, cutting complex CTB assessments from up to two days to under an hour. The solution delivered about a 15% improvement in planning efficiency, eliminated daily manual shortage reporting (≈4 hours/day), saved roughly 35 planner hours/week in the first account, freed planners for higher‑value work, and sustained or slightly improved on‑time delivery.