The customer, Keller, a piling contractor, faced the challenge of supplying a massive number of prefabricated pile cages for the Darlington Upgrade Project, the largest piling job ever undertaken in South Australia. This demand was further complicated as it ran concurrently with another major project. Keller collaborated with vendor InfraBuild Reinforcing to supply over 4000 tonnes of these cages.
To meet this challenge, InfraBuild established a new facility at Angle Park and significantly scaled its operations, increasing its number of pile cage machines from one to five. This investment in equipment and a detailed fabrication process allowed InfraBuild to streamline production and successfully supply all required materials, overcoming complex logistical challenges associated with transporting oversized loads.