Frankipile faced significant challenges during remedial piling works at the remote Yandi Iron Ore Mine, including high delivery and labour costs, and the potential for delays due to on-site steel fixing errors. These issues convinced the builder to partner with InfraBuild for a prefabricated pile cage solution.

InfraBuild supplied 230 prefabricated pile cages, manufacturing them at a rate of six units per day. To ensure the cages survived the 2100 km transport journey without damage, InfraBuild implemented stringent quality control and designed a special anti-crush brace. This solution provided Frankipile with a high-quality, efficient product that eliminated the risk of on-site fabrication errors and delays.