InfraBuild
161 Case Studies
A InfraBuild Case Study
Frankipile faced significant challenges during remedial piling works at the remote Yandi Iron Ore Mine, including high delivery and labour costs, and the potential for delays due to on-site steel fixing errors. These issues convinced the builder to partner with InfraBuild for a prefabricated pile cage solution.
InfraBuild supplied 230 prefabricated pile cages, manufacturing them at a rate of six units per day. To ensure the cages survived the 2100 km transport journey without damage, InfraBuild implemented stringent quality control and designed a special anti-crush brace. This solution provided Frankipile with a high-quality, efficient product that eliminated the risk of on-site fabrication errors and delays.