Foodland Associated Ltd (FAL) faced the challenge of constructing the steel roof for its massive new 54,000sqm distribution warehouse in Perth. The project required safely and efficiently laying roof trusses across spans of up to 40 meters. InfraBuild supplied the steel for this large-scale project.
InfraBuild's steel was used by fabricator Fremantle Steel Fabrication Co. in an unconventional solution. The entire roof structure was pre-assembled in sections on the ground and then hoisted into place by cranes. This technique was judged the safest and most effective method, and it enabled InfraBuild's partners to complete the steelwork substantially ahead of schedule.