InfraBuild
161 Case Studies
A InfraBuild Case Study
Beenleigh Steel Fabrications required structural steel beams for a major high-rise construction project in Brisbane that would allow for lighter sections and reduced floor depth, a challenge that demanded specialized processing. InfraBuild provided its service of supplying pre-cambered structural steel sections from its Coopers Plains branch to meet this need.
The solution implemented by InfraBuild utilized its in-house cambering machine to pre-set deflection in the beams, which eliminated the need for third-party processing. This integrated service resulted in a significantly streamlined supply chain, reducing the fabricator's turnaround time from two or three weeks to just one week and contributing to the rapid pace of construction.