Case Study: a consumer goods manufacturer cuts Oracle Fusion rollout from 8 months to 5 with InfoBeans

A InfoBeans Case Study

Preview of the A Consumer Goods Manufacturer Case Study

How a consumer goods manufacturer took a three pillar Fusion rollout from 8 months to 5

A consumer goods manufacturer faced a significant challenge with a fixed go-live date for its three-pillar Oracle Fusion rollout. The project, involving Financials, Procurement, and Supply Chain, was at risk due to slow first-draft FDD creation and configuration gaps that only surfaced after system integration testing had begun, compressing a testing phase budgeted for seven months. InfoBeans was engaged to address these issues.

InfoBeans implemented a solution where all three workstreams started from the same requirements and Oracle process list. This approach delivered first FDD drafts in just four days and allowed configuration to be checked before testing. As a result, InfoBeans helped reduce the total time from requirements to go-live from eight months to five, and combined testing was completed in under three months, ensuring the program met its fixed deadline.


View this case study…

InfoBeans

114 Case Studies