Superior Construction, a fourth-generation infrastructure contractor, faced the challenge of managing thousands of documents on the $320-million Indiana Department of Transportation North Split interchange project. INDOT’s use of SharePoint lacked the functionality needed for a large, multi-year program, so Superior sought a more robust collaborative document-control solution and selected InEight Document from InEight.
Using InEight Document, Superior customized and deployed an intuitive system that automated recurring submittals and streamlined review workflows. By the project midpoint the team had processed more than 1,300 documents, automated roughly 80% of submittal traffic, reduced repetitive processing time by hours per user, and achieved measurable cost and productivity gains while improving overall project control.
Josh Kistner
Project Controls Manager, North Split Project