Mitchell Mill Systems, a manufacturer of material handling equipment, faced a challenge to increase efficiency as part of a company-wide lean initiative. The project manager was tasked with reducing cutting time, material, and labor costs in their fabrication process, which utilized a mechanized plasma cutting table. To meet this challenge, they evaluated Hypertherm's ProNest LT nesting software.
Hypertherm's ProNest LT software delivered a professional-grade nesting solution that dramatically sped up programming. A time study revealed it reduced nesting time by 74%, cutting the process from 12.5 minutes down to just 3 minutes per job. This resulted in calculated labor savings of 85 hours and $6,375 annually. Furthermore, the software's advanced cutting techniques improved part quality so significantly that the company was able to eliminate costly secondary operations, such as reaming holes.