Family Health Centers of San Diego required assistance managing the final general contractor selection and construction of a new 23,000-square-foot medical office building. The project faced substantial delays from client changes and permit acquisition, which threatened its timeline. Hughes Marino was selected to provide project management services to help address these challenges.

Hughes Marino worked closely with the team to mitigate delays, including negotiating with city staff on the scope of offsite improvement work. This diligent project management helped minimize setbacks and resulted in significant cost savings for the client. Hughes Marino successfully saved Family Health Centers of San Diego over $120,000 on the project.