Hexagon PPM
92 Case Studies
A Hexagon PPM Case Study
Rishabh Engineering Services, a division of Rishabh Software in India, needed to develop a 3D model for a brownfield expansion of an Oklahoma oil storage facility with limited starting information. The team had no site or equipment layout and had to route piping from civil survey points over uneven ground while keeping the project accurate and efficient. Hexagon PPM’s CADWorx Plant Professional was used to support the effort.
Using Hexagon PPM’s CADWorx, Rishabh Engineering Services created a detailed 3D model, isometric drawings, bills of material, and other deliverables with minimal input. The software helped improve accuracy, reduce training time by 20%, and cut project time by 5%; the team completed work that required 2,000 man-hours in just 2.5 months with five people, helping ensure client satisfaction.
Arpit Gupta
Manager of Business Development