Mahler AGS, a manufacturer of gas generation plants, faced a tight project schedule and challenges with mixed piping codes for a new modular hydrogen plant. They needed to replace their existing design software with a modern, easy-to-use, and AutoCAD-compatible 3D planning solution to minimize downtime. They chose Hexagon PPM's CADWorx Plant Professional and CAESAR II software for the project.
By implementing Hexagon PPM's solutions, Mahler AGS completed the plant design in approximately five months. The software's ease of use and compatibility led to a 10-15% reduction in overall project work-hours and a 25-30% time savings on stress calculations. The success of this project led Mahler to adopt these solutions for all future plant designs.