Case Study: Australian LNG Upstream Phase 1 Project simplifies well handover with Hexagon PPM Smart Completions

A Hexagon PPM Case Study

Australian LNG Upstream Phase 1 Project cuts well commissioning dossier time by over 98% with Hexagon PPM

The Australian LNG Upstream Phase 1 Project sought to improve its well handover and completion process, which was manual and time-consuming. The challenge for the field delivery and well commissioning and stabilization team was to combine innovation and collaboration to develop a best practice approach. To address this, they worked with Hexagon PPM and its Intergraph Smart Completions software to create a more streamlined and automated system.

Hexagon PPM's solution involved implementing Intergraph Smart Completions to automate the compilation of commissioning dossiers. This resulted in a vastly simplified process, allowing electronic documentation to be completed and uploaded automatically. The measurable impact was substantial, as the new process will compile 977 well commissioning dossiers in less than 2 percent of the time it took to generate them manually.


View this case study…

Hexagon PPM

132 Case Studies