W. Webber Construction’s Utilities Division in The Woodlands, TX, led by Estimating Manager Syd Jones, builds complex water and wastewater treatment projects that typically require a four- to five-week estimating effort. The division lacked standardized quantities and true bid history, and several sister teams still relied on fragile spreadsheets, making it time-consuming to recreate bid forms and risky to manage last-minute changes.
By adopting HCSS HeavyBid, Jones created master estimates and activity libraries as templates for pump stations, water plants and wastewater projects, and he imports non-HeavyBid numbers from other divisions as subcontractor inputs. The team can make tracked, line-item adjustments with a clear audit trail, cutting estimating time roughly in half, eliminating spreadsheet corruption, and increasing confidence in cost accuracy at bid time.