Case Study: Upper Styria hydropower plant achieves rapid construction continuity with Hawle

A Hawle Case Study

Preview of the Upper Styria hydropower plant Case Study

Upper Styria hydropower plant

The customer, Upper Styria hydropower plant, faced a challenge at its construction site where unscheduled changes required a rapid delivery of parts to maintain the water supply and avoid costly delays. The vendor, Hawle, provided a solution involving flange adapters and a DN 1000 connection.

Hawle successfully delivered the required parts in just three weeks, a significant reduction from the standard eight-week lead time. This rapid delivery allowed construction to continue without interruption and saved the customer from incurring costly contractual penalties.