QTS, a leading provider of data center solutions, selected Gray Construction to complete the fit-out for two new data centers on its campus in New Albany, Ohio. The challenge was to build these large-scale, high-capacity facilities to meet the company's expanding needs.

Gray constructed two Tier 4 data centers with a combined capacity of 78 MW, operational within 17 months. This project established a new campus for QTS and is part of a larger planned investment exceeding $1.5 billion, with two additional data centers planned for an adjacent site. Gray's successful delivery of this initial phase helped support significant market growth for QTS.