Case Study: C. L. Heilman accelerates bridge construction with Giatec SmartRock sensors

A Giatec Case Study

Preview of the C. L. Heilman Company, Inc. Case Study

C. L. Heilman Company, Inc. - Customer Case Study

C. L. Heilman Company, Inc., a specialized bridge construction firm, faced the challenge of complying with a new Idaho mandate requiring ASTM C1074 maturity testing to confirm concrete strength on a major interchange project. The company sought a more efficient alternative to labor-intensive wired sensors to reduce man-hours and avoid delays from lab results. They turned to vendor Giatec for a solution.

Giatec's wireless SmartRock sensors provided the solution, enabling real-time monitoring of concrete temperature and strength data via a mobile app. This eliminated the wait for lab reports and streamlined the inspection process. The implementation resulted in significant time savings, with Heilman estimating they shaved five-to-ten days off their schedule and completed the work 10 to 15 percent faster by using Giatec's technology.


View this case study…

C. L. Heilman Company, Inc.

James Heilman

VP and Co-Owner


Giatec