The customer, Besco, faced significant schedule pressure on the Alameda Central Stage 2 social housing project in Lima, Peru. With a fixed 11-month deadline, traditional concrete strength testing created delays of 3 to 7 days per slab, increasing costs and risk. To overcome this challenge, Besco worked with the vendor Giatec to implement its SmartRock sensors and SmartRock Web platform for real-time concrete monitoring.
Giatec's solution provided real-time strength data using the maturity method, replacing the need to wait for lab results. This enabled Besco to release slabs an estimated 3 days faster, accelerating the structural cycle by 32%. The project also achieved up to 15% cement reduction and 90% fewer destructive tests, leading to concrete-related cost savings of approximately 18-20% and total direct savings of up to $120,000, all while maintaining compliance and quality with zero concrete rejections.