Genesis Petroleum Technologies
2 Case Studies
A Genesis Petroleum Technologies Case Study
Genesis Petroleum Technologies worked with Anadarko Petroleum Corporation, which faced a challenge in utilizing the large amounts of data generated from its daily drilling operations in West Central Canada. The data was not being used effectively to shorten the learning curve and improve overall drilling efficiency.
The solution implemented by Genesis Petroleum Technologies was a drilling analysis methodology based on establishing a Best Composite Time (BCT), or practical Technical Limit. This method created a well plan using the best times ever achieved for any single operation, establishing a continuously improving performance target. By applying this tool, Anadarko achieved significant cost savings of CAD$7 million during the period it was measured.