Galooli
12 Case Studies
A Galooli Case Study
A major telco operating roughly 5,000 sites was facing excessive energy costs due to inefficient cooling system logic at its sites. The operator lacked visibility into key data points like indoor versus outdoor temperatures and cooling setpoints, which prevented them from identifying the root cause of the waste. They partnered with Galooli to address this challenge.
Galooli deployed real-time monitoring to identify the issue: air conditioning units were engaging prematurely instead of using more efficient fans. Galooli then pushed an over-the-air configuration update to reprioritize fan usage and automate cooling to defined setpoints, requiring no site visit or new hardware. This remote fix resulted in a 33% reduction in average energy consumption, extended equipment lifecycles, and eliminated the need for CAPEX on external cooling controllers.
Major Telco Operating Roughly 5,000 Sites