The customer, Holiday Retirement, sought an energy-efficient lighting retrofit for 15 senior living facilities to improve lighting levels and resident safety. Their challenge involved inconsistent and frequently broken existing fixtures. Facility Solutions Group was engaged to provide a solution.

Facility Solutions Group designed and implemented a uniform lighting solution, coordinating crews to perform simultaneous nationwide installations with minimal disruption. They replaced over 4,500 fixtures, achieving annual energy savings of approximately 600,000 kWh and $60,000 for the customer.