A Facility Solutions Group Case Study
The customer, JB3 Water Booster Station, is a facility built as part of a major regional water supply initiative to ensure future water availability for the growing Dallas-Fort Worth area. Their challenge was to construct and power a massive new water booster station from the ground up, requiring a highly experienced electrical contractor. Facility Solutions Group (FSG) was selected as the trusted vendor to provide the electrical construction services for this critical project.
Facility Solutions Group utilized its dedicated water/wastewater team to execute the ground-up electrical construction. The team installed approximately 300,000 feet of electrical conduit over two years to fully power the enormous station, which houses the world's largest gate valve. The solution implemented by FSG successfully enabled the JB3 Water Booster Station to become operational, achieving its massive goal of moving 350 million gallons of water per day to 80 cities.
JB3 Water Booster Station