Environmental Resources Management (ERM)
77 Case Studies
A Environmental Resources Management (ERM) Case Study
A major utility company faced the challenge of navigating the complex development of a 118 MWac solar project on 900 acres in Virginia. The project risked delays, increased costs, and public opposition due to environmental assessments, zoning approvals, and civil engineering requirements. Environmental Resources Management (ERM) was engaged to provide project management and environmental due diligence services.
ERM conducted environmental surveys, managed permitting and zoning approvals, and designed erosion and stormwater controls. The vendor's work led to successful site plan approval and permit coverage, enabling project construction to proceed. ERM mitigated risks, ensured regulatory compliance, and prevented potential delays, demonstrating their role as an expert and innovative partner.
Major Utility Company