Curtis Bay Energy is a 24/7 medical waste disposal company that processes about 150 tons of biohazard waste per day and uses the resulting energy to power its facility. Facing increasingly strict emissions standards, the 11‑person maintenance team needed a simple, reliable maintenance management system to plan major equipment overhauls and outages, track work orders and inventory, and stay organized during large renovation projects.
After attending eMaint training and summits, Curtis Bay implemented the system—loading ~1,000 assets in two months, consolidating work orders into project trackers, and using a sandbox for testing—supported by a dedicated account manager. The result: real‑time equipment and work‑order tracking, stronger compliance with emissions requirements, added SOPs and preventive maintenance schedules, and a $150,000 reduction in maintenance costs on a single project through better parts requirement projections.