A major food distributor faced significant challenges when a project to integrate a conveyor system with their pocket filler, vacuum filler, and steamer fell behind schedule. The project suffered from understaffed controls support and incomplete work, compounded by a previous controls integrator leaving the site. The distributor turned to E Tech Group for its system integration expertise to create a clear plan and overcome these obstacles.
E Tech Group staffed the project with skilled engineers who assessed the situation and created a comprehensive punch list. They developed a new controls strategy, corrected electrical issues, and standardized the programming to successfully integrate the conveyor system with the existing OEM equipment. As a result, E Tech Group restored the project's trajectory within weeks, an achievement that built considerable trust and led the customer to engage them for three additional projects.