Mota-Engil, an international mining company, was faced with the challenge of sourcing twelve high-flow pumpsets for its operation in Mozambique's Tete region with an extremely demanding three-month delivery window. DXB Pump & Power was approached to supply this critical equipment, which needed to be robust and highly reliable to ensure zero breakdowns.
DXB Pump & Power immediately coordinated with key suppliers like Cornell Pump and Caterpillar to confirm the aggressive timeline was feasible. The company then dedicated six weeks of intensive work, building custom trailer-mounted pumpsets complete with safety and protection systems. As a result, DXB successfully delivered all twelve powerful pumpsets on time and on budget, enabling the mine to install and operate them within the strict twelve-week timeframe.