Blackwater Aggregates, a joint venture between Cemex and Gent-Fairhead Aggregates operating a large sand and gravel quarry in Essex, UK, faced the challenge of upgrading a critical 15-year-old water pump. The existing pump had over 40,000 hours of operation and the company sought a modern solution from DXB Pump & Power to significantly reduce costs and emissions while maintaining the water supply essential for their washplant operations.
DXB Pump & Power supplied a new, fully enclosed pumpset with a modern Stage 5 engine. The solution delivered the same performance of 400m³/hr at 4 bar but used 95kw of power instead of the previous 140kw. This resulted in a 90% decrease in harmful emissions and a substantial reduction in fuel consumption and running costs, while future upgrades will enable remote management. DXB Pump & Power's solution provided a model 21st-century water management system for the quarry.