A Dusty Robotics Case Study
Jenco, an electrical contractor in Arizona, faced challenges with accuracy, communication, and labor efficiency on a large manufacturing facility project. They sought a way to shorten the project schedule and save costs. Jenco turned to vendor Dusty Robotics and its solution for automated, multi-trade layout to address these issues.
By implementing Dusty's multi-trade layout process, all trades were printed at the same time, allowing problems to be identified and solved before construction began. This solution saved Jenco $80,000 in direct layout costs on the single project and allowed them to finish six weeks ahead of schedule. Dusty Robotics eliminated rework, improved labor allocation, and provided Jenco with a significant competitive advantage.
David Meacham
Project Executive