Case Study: Deacon Construction saves $2.5M and finishes six weeks early with Dusty Robotics

A Dusty Robotics Case Study

Preview of the Deacon Construction Case Study

Deacon Construction saves $2.5M and finishes 6 weeks early with Dusty Robotics

Deacon Construction faced the challenge of mitigating coordination risks and avoiding costly rework on a complex, $18M healthcare tenant improvement project. To achieve this, they utilized the FieldPrinter from vendor Dusty Robotics to provide a precise, multi-trade layout early in the schedule.

The solution from Dusty Robotics created a single source of truth for all trades, enabling a major shift in construction sequencing. This allowed the HVAC trade to install from lifts in an open space before walls were built, which doubled their production speed. The results for Deacon included finishing six weeks early, saving $2.5 million for the project owner, and completing the project with zero safety incidents.