Eggborough Power, a UK electricity generator operating since the 1960s and supplying enough energy to power about 2 million homes, needed a better way to monitor plant performance. Relying on daily manual scans of large databases to find anomalies was slow and ineffective, making it hard to identify opportunities to reduce waste and costs.
Business Systems Architect Chris Phillipson implemented Dundas Dashboards to track unit performance, cost of losses and spending in real time, replacing the old reporting process. The dashboards were quick to deploy and use, helped cut around £600,000 from electricity costs, sped up analysis and improved alarm-system and health-and-safety monitoring, making the plant safer and more efficient.
Chris Phillipson
Business Systems Architect, Eggborough Power