northeastern u.s. utility protects hospital circuits with 5 Davey crews during COVID-19

Davey Resource Group (DRG) assisted a major electric utility in the Northeastern U.S. The challenge was to prevent power outages at hospitals during the COVID-19 pandemic by urgently addressing vegetation threats to critical electrical circuits.

DRG deployed a team to conduct intensive inspections of hospital-feeding circuits using their proprietary field software. They identified hazardous vegetation and coordinated its immediate removal via a paperless workflow, ensuring social distancing. DRG's solution provided the utility with a reliable process to safeguard power to healthcare facilities, giving their employees a strong sense of purpose during the crisis.