Hoosier Energy, a Midwestern U.S. based utility, faced a tight deadline for an 18-mile natural gas pipeline project in Indiana. All logistical work was complete, but no environmental surveys or permit coordination had been done, risking the construction schedule. They turned to Davey Resource Group for urgent environmental planning and permitting services.
Davey conducted swift field surveys, GIS analysis, and agency coordination to locate wetlands and confirm the absence of endangered species. Their team secured all necessary permits from the US Army Corps of Engineers and Indiana state agencies. As a result, Davey enabled the pipeline construction to proceed on schedule and continues to manage ongoing mitigation to ensure permit compliance for the utility.