Dassault Systemes
412 Case Studies
A Dassault Systemes Case Study
Global Unichip Corporation (GUC), a leading Taiwanese IC design company, faced slowed time-to-market, poor project schedule control and quality assurance due to siloed departments, manual weekly updates and a complex external supply chain. To address these challenges, GUC selected Dassault Systemes’ ENOVIA V6 collaborative PLM platform.
Dassault Systemes implemented ENOVIA V6 in phased rollouts (integrating 20 Lotus Notes systems) to provide a unified project-management and collaboration framework. The solution delivered real‑time project status, automated reporting and cross‑partner collaboration, cutting quote preparation from three weeks to one week and improving issue resolution from 24% to 55% within three months, while reducing R&D costs and helping GUC meet time‑to‑market objectives.
Albert Li
Director of Design Development Division