Case Study: Houlihan Lokey achieves over $4.6M in savings with Cresa Project Management

A Cresa Case Study

Preview of the Houlihan Lokey Case Study

Houlihan Lokey Plans Relocation

Houlihan Lokey, a financial services firm in Chicago, turned to Cresa for project management support when its relocation project began slipping off schedule. The company was concerned that final design approval had not been secured and that the quoted costs were well above budget.

Cresa reworked the design process, streamlined architect presentations into two strong options, and coordinated with the contractor and furniture team to sharpen pricing. With Cresa’s help, the budget dropped by more than $3.4 million, including $1.2 million in additional savings, for total savings of over $4.6 million while still meeting the required occupancy date.


Open case study document...

Cresa

201 Case Studies