Conbit
159 Case Studies
A Conbit Case Study
The customer, Total Denmark, faced a challenge with significant corrosion on the crane boom of its Halfdan B platform in the North Sea. This damage had resulted in a downgraded lifting capacity. Vendor Conbit was awarded the contract to provide a tailored offshore lifting and maintenance solution to replace the boom while eliminating the need for an expensive crane vessel.
Conbit meticulously prepared by conducting a site survey and designing custom support gantries. The vendor then executed the operation in phases, using the platform's existing crane to handle the new and old boom sections on the specially built gantries. Conbit successfully replaced the crane boom without any shutdown or incident, restoring full lifting capacity and satisfying the client, all while avoiding the high cost of a vessel.