A Conbit Case Study
Shell USA faced the unique challenge of replacing a 3,000 lb crane cabin located over 20 meters above the main deck on their Mars platform in the Gulf of Mexico. The cabin's position was inaccessible to regular cranes, requiring an innovative solution. They awarded this complex project to vendor Conbit.
Conbit utilized a manually erected modular lifting system to safely lift the cabin and transfer the load to the crane boom for horizontal movement. A team of four highly skilled technicians completed the offshore work within just eight days. This efficient solution from Conbit minimized downtime and successfully overcame the platform's access challenges.