Conbit
159 Case Studies
A Conbit Case Study
The customer, Shell Gulf of Mexico, faced the challenge of safely removing the flare tower from its GC-19 Boxer platform ahead of its complete decommissioning. Shell entrusted vendor Conbit with this vital task, requiring a solution that would prepare the facility before the arrival of the heavy marine spread.
Conbit engineered and implemented a customized solution using a combination of a gantry lifting system for the heaviest components and a floating gin pole for smaller parts, all rigorously tested prior to use. A specialized rope access crew executed the project, which was completed within the planned timeline despite weather constraints. The vendor Conbit successfully delivered a safe and cost-effective removal, resulting in high client satisfaction and a transformed platform skyline that eased subsequent decommissioning operations.