PTTEP resumes production 1 day earlier with Conbit's flare tip replacement

The customer, PTTEP, faced the challenge of performing a flare tip replacement at their Bongkot North gas field where extremely limited space between two decks created significant obstacles. They requested the vendor, Conbit, to develop a solution for this complex maintenance operation.

Conbit developed an integrated solution that involved advanced planning, a crucial site visit, and the strategic installation of a davit crane and winch in the confined space. The vendor's team successfully executed the procedure, which included rotating and lowering the old flare tip before installing the new one. As a result of Conbit's work, the operation was completed safely and ahead of schedule, shortening the shutdown period and allowing production to resume a full day earlier.