Petronas Carigali, through its contractors Technip and MMHE, was developing the new SK316 Central Processing Platform and required a safe and efficient method for future flare tip replacement on the offshore platform. The vendor Conbit was contracted by flare tip manufacturer GBA to conduct a handling study and design a solution for this challenge.
Conbit engineered a unique mechanical handling system using modular equipment, including a high-speed lift winch on the deck and a lightweight aluminum gantry structure on the flare tip access platform. This solution from Conbit enables the rigging crew to safely lower a flare tip over the side of the platform so it can be directly lifted onto a supply vessel, ensuring future replacements will be efficient and minimizing the system's overall weight.