The customer Petrobras faced the challenge of planning for the future replacement of four flare tips on their F80 FPSO vessel offshore Brazil. The operation was complex due to the limited space on the single flare tower top platform and the significant height differences involved. Vendor Conbit was enlisted to engineer a safe and practical handling methodology for this task.
Conbit engineered a dedicated gantry lifting system, consisting of a 9.7 m high gantry and a 6 mT winch, to provide the necessary clearance to move the heavy flare tips. This solution provided Petrobras with a defined and practical methodology for carrying out the future flare tip replacements during a shutdown, taking into account the existing platform structure and all required equipment interfaces.